Government procurement post-Carillion
In March 2020, the well-regarded Institute for Government (IfG) think tank held an event to mark the launch of a report looking into Government outsourcing and procurement post the collapse of Carillion.
Construction giant Carillion fell into liquidation in January 2018. Prior to this, Carillion had been one of the Government’s largest suppliers, undertaking a range of work of construction and facilities management activity, across various sectors.
However, an inquiry from the Business and the Work and Pensions Select Committees later found its collapse was "a story of recklessness, hubris and greed, its business model was a relentless dash for cash."
In fact, Carillion owed its suppliers and subcontractors hundreds of millions of pounds. Much of this was either payment due for completed work, or retentions held on work already undertaken. The suppliers never received their money back.
So, two years on, the Institute for Government sought to review how the Government is now approaching outsourcing, and what still needs to change.
On the day, a panel consisting of IfG (Tom Sasse and Nick Davies), CBI (Liz Crowhurst, Head of Infrastructure) and Shaw Trust (Chris Luck, CEO) discussed the findings of the report.
The panellists concurred that the principles of the Government's ‘outsourcing playbook’, developed after the collapse of Carillion, were sound. However, it was found that these principles are not yet being universally applied throughout Government.
The report also made a number of sensible recommendations, notably:
- Name a Cabinet Office minister who is responsible for improvements in outsourcing.
- Use this summer’s spending review to give the Cabinet Office funding to support and scrutinise contracting by departments.
- Extend contracting training to local government, the NHS, and other public bodies.
- Equip the new Audit, Reporting and Governance Authority with the statutory powers recommended by the Kingman review, including to force changes in company accounts rather than applying to court to do so.
These are sensible reforms which have the support of ECA, alongside the Government’s new requirement to remove late payers from the tendering process.
However, as report author Tom Sasse commented, "the race to the bottom on price is probably the biggest problem we have in contracting". Looking ahead, how the Government approaches this challenging issue will be fundamental to whether we see real change in procurement.
Our hope and expectation is that the Government will accelerate implementation of the Construction Leadership Council’s Business Model’s workstream output on Procuring for Value. This industry collaboration focused on the creation and establishment of a procurement model focused on the whole-life cost of the built asset, not just the construction cost.
In which case, procurement could finally be based on value rather than price…
You can view the report here - https://www.instituteforgovernment.org.uk/sites/default/files/publications/carillion-two-years-on.pdf
This article was originally published on the ECA blog on 13 March 2020. It was written by Rob Driscoll, Director of Legal & Business at ECA.
--ECA
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
How can digital twins boost profitability within construction?
A brief description of a smart construction dashboard, collecting as-built data, as a s site changes forming an accurate digital twin.
Unlocking surplus public defence land and more to speed up the delivery of housing.
The Planning and Infrastructure bill oulined
With reactions from IHBC and others on its potential impacts.
Farnborough College Unveils its Half-house for Sustainable Construction Training.
Spring Statement 2025 with reactions from industry
Confirming previously announced funding, and welfare changes amid adjusted growth forecast.
Scottish Government responds to Grenfell report
As fund for unsafe cladding assessments is launched.
CLC and BSR process map for HRB approvals
One of the initial outputs of their weekly BSR meetings.
Architects Academy at an insulation manufacturing facility
Programme of technical engagement for aspiring designers.
Building Safety Levy technical consultation response
Details of the planned levy now due in 2026.
Great British Energy install solar on school and NHS sites
200 schools and 200 NHS sites to get solar systems, as first project of the newly formed government initiative.
600 million for 60,000 more skilled construction workers
Announced by Treasury ahead of the Spring Statement.
The restoration of the novelist’s birthplace in Eastwood.
Life Critical Fire Safety External Wall System LCFS EWS
Breaking down what is meant by this now often used term.
PAC report on the Remediation of Dangerous Cladding
Recommendations on workforce, transparency, support, insurance, funding, fraud and mismanagement.
New towns, expanded settlements and housing delivery
Modular inquiry asks if new towns and expanded settlements are an effective means of delivering housing.
Building Engineering Business Survey Q1 2025
Survey shows growth remains flat as skill shortages and volatile pricing persist.